PSC approves Cardinal-Hickory Creek power line

Get Our Email Newsletter
The companies, people and issues shaping business in Madison and the Capital Region.

The state Public Service Commission has granted preliminary approval to build the Cardinal-Hickory Creek power line between Middleton and Dubuque, Iowa.

The high-voltage transmission line is expected to cost $492 million and while controversial, commissioners believe it will help Wisconsin make the transition from fossil fuels to a clean energy grid and save money for Wisconsin ratepayers, according to an article in the Wisconsin State Journal. A final written order from the PSC, which could be subject to further approval, could come in September.

The transmission line is a joint venture of American Transmission Co., ITC Midwest, and Dairyland Power Cooperative.