Improvements and repairs to the city of Madison bike network will be covered by its Bikeways 2023 contract. The three projects below have been identified by planners and residents as crucial missing connections for bike accessibility, safety, and comfort.

  • UW Arboretum: 

Starting today, Seminole Highway at the UW Arboretum entrance will see a change in traffic control and possible flagging of traffic. Plans include a 10-foot shared use path connecting Manitou Way with McCaffrey Drive, which is the western entrance to the UW Arboretum, and the installation of a rectangular rapid flashing beacon pedestrian crossing.

Seminole Highway will remain open in both directions for the duration of the project. Construction is anticipated to conclude in July.

  • West Lakeside Street:

Starting on Monday, June 24, West Lakeside Street from Gilson Street to Rowell Street will be closed. Plans include an off-street, two-way cycle track on the south side of West Lakeside Street connecting two sides of the Bay Creek Neighborhood in south Madison, removal of parking on the block, pavement replacement, and new curb and gutter.

West Lakeside Street will remain closed for the duration of the project except for local traffic. Sidewalks will remain open on at least one side for the duration of the project. Construction is anticipated to conclude in mid-July.

  • Elver and Greentree Park Path:

Starting on Monday, July 22, Elver park path between McKenna Boulevard and South Gammon Road and a section of the Greentree Park Path north of McKenna Boulevard will be affected. Plans include repairs to the path and construction of a new culvert at the north end of the path to improve drainage.

Elver Park Path and Greentree Park Path may be closed during some or all of construction. Work is anticipated to conclude in early August.